Application For Transmission Line Filed With PUC

BROOKINGS, S.D. (AP) — Otter Tail Power Company and Xcel Energy have filed a permit application with the South Dakota Public Utilities Commission for a high-voltage transmission line from Big Stone City to near Brookings.

The 70-mile 345-kilovolt line would run between a new substation about three miles west of Big Stone City and the existing Brookings County substation 12 miles east of Brookings.

The permit covers the southern 40-mile portion of the project from just north of Gary to Brookings County. The goal is to have the line operational by 2017.

The Minnesota-based companies are part of CapX2020, a joint initiative of 11 transmission-owning utilities.

The South Dakota Public Utilities Commission is planning to hold a public meeting to gather comments from residents July 31 at 6:30 p.m. at McCrory Gardens in Brookings.

(© Copyright 2013 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)

Comments

Leave a Reply

Fill in your details below or click an icon to log in:

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

More From WCCO | CBS Minnesota

The Leaderboard
Good Question
%d bloggers like this:

Listen Live