BROOKINGS, S.D. (AP) — Otter Tail Power Company and Xcel Energy have filed a permit application with the South Dakota Public Utilities Commission for a high-voltage transmission line from Big Stone City to near Brookings.

The 70-mile 345-kilovolt line would run between a new substation about three miles west of Big Stone City and the existing Brookings County substation 12 miles east of Brookings.

The permit covers the southern 40-mile portion of the project from just north of Gary to Brookings County. The goal is to have the line operational by 2017.

The Minnesota-based companies are part of CapX2020, a joint initiative of 11 transmission-owning utilities.

The South Dakota Public Utilities Commission is planning to hold a public meeting to gather comments from residents July 31 at 6:30 p.m. at McCrory Gardens in Brookings.

(© Copyright 2013 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.