Demolition Crews Begin Tearing Down Metrodome Walls

MINNEAPOLIS (WCCO) — It’s a milestone week in the demolition of the Metrodome, with crews starting to knock holes in the exterior walls, starting with the northeast corner.

It’s a rugged yet meticulous process, bringing down a stadium that used to have the nickname Thunder Dome. Now, all the decibels are coming from heavy machinery, smashing steel and concrete, section by section.

Allen Troshinsky is Director of Operations for Mortenson Construction’s sports group.

“As the weeks progress,” he said, “you’ll see coming out of that northeast corner, the hole in the building opening up and working its way in two directions both clockwise and counter-clockwise.”

Blowing up the stadium with explosives would have caused too much dust and vibration to other downtown buildings, so crews are using a wrecking ball and a high reach excavating machine with a “muncher” attachment, which severs the structure.

“They’ll go in and strategically make structural cuts in the concrete or the steel,” said Troshinksy, “and cause elements to collapse.”

Crews took all the seats out of the Metrodome weeks ago. And now, 90 percent of what’s left is going off to reclaiming and recycling facilities.

“Scrap steel is recycled into new steel and that could go into possibly new construction,” Troshinksy said.

Several people are starting to turn out, to take in the sight for themselves.

“It’s kind of bittersweet,” said Grant Niver of Minneapolis. “Obviously a lot of good memories at the Dome, but it’ll be exciting to see the new one go up.”

Tony Curtis of Brooklyn Park is able to watch the demolition from the federal office building, where he works, but he drove to the site to get a closer look.

“I’m not really a fan,” he said, “but still, it’s part of Minnesota, you know?”

Mortenson expects all of the Dome’s walls to be down by the end of April. Crews are on schedule despite the cold, but they’re hoping for an extended warm-up.

“The equipment works better, our people are a little happier to be in the warmer climates,” said Troshinsky.

At the same time the Dome comes down, construction on the new stadium is well underway. Some of the wall foundations are going in this week, in what used to be the east parking lot.

More from Mike Binkley
  • andrewhagle

    Reblogged this on Home Grown News Media.

  • Demolition Crews Begin Tearing Down Metrodome Walls | The Best Weight Loss Programs
  • Minnesota Vikings Fan Club of New Mexico for football fans in the Rio Rancho and Albuquerque area at Slate Street Billiards « Minnesota Vikings Fan Club of New Mexico

    […] By Cole Premo […]

  • Metrodome Demolition: Minnesota Vikings Football Stadium Comes Down. Moley Magnetics INC

    […] It took more than two years to build the Metrodome; it took considerably less time to tear it down. Some of the wall foundations are going in, in what used to be the east parking lot.  The original demolition plan didn’t include the use of explosives, but last week crews decided it would be the best option. The explosive demolition went off without a hitch, according to Mortenson Construction vice president John Wood. The blast was meant to bring down only the upper ring of the structure, after an expected collapse as that was being demolished last week. “It was a complete success. It is laying on the ground,” Wood said. “That was mission accomplished… It went exactly as planned.” At the same time the Dome comes down, construction on the new stadium is well underway. The arena, under demolition, is making way for a new and presumably much better facility, scheduled to open in July 2016. Read entire article at […]

  • Demolition of Dome on hold after beam falls unexpectedly | TwinCitiesLand News

    […] of the 22-year-old stadium has been moving forward quickly. Last week a wrecking ball began knocking down the walls, WCCO […]

blog comments powered by Disqus
Thursday Night Football

Listen Live